๐๐๐ฅ๐๐ฒ ๐ฐ๐ก๐๐ง ๐๐๐ฎ๐ฌ๐๐ ๐๐ฒ ๐๐จ๐ญ๐ก ๐ญ๐ก๐ ๐๐๐ซ๐ญ๐ข๐๐ฌ ๐ข๐ง ๐๐จ๐ง๐ฌ๐ญ๐ซ๐ฎ๐๐ญ๐ข๐จ๐ง ๐๐จ๐ง๐ญ๐ซ๐๐๐ญ๐ฌ: ๐๐ฎ๐ฉ๐ซ๐๐ฆ๐ ๐๐จ๐ฎ๐ซ๐ญ ๐๐ง๐ญ๐ซ๐จ๐๐ฎ๐๐๐ฌ ๐ญ๐ก๐ ๐๐จ๐ง๐๐๐ฉ๐ญ ๐จ๐ ๐๐จ๐ง๐๐ฎ๐ซ๐ซ๐๐ง๐ญ ๐๐๐ฅ๐๐ฒ๐ฌ ๐ข๐ง๐ญ๐จ ๐จ๐ฎ๐ซ ๐๐ฎ๐ซ๐ข๐ฌ๐๐ข๐๐ญ๐ข๐จ๐ง ๐๐จ๐ซ ๐ญ๐ก๐ ๐ ๐ข๐ซ๐ฌ๐ญ ๐๐ข๐ฆ๐.
The question arises that what would be the solution if delay or delays are caused by two events of equal causative potency and one event is attributed to contractor and the other to employer? Or where the delays are caused by two events of equal causative potency one relevant and the other not relevant?
This scenario is called concurrent delays which means that timely execution of a project is delayed by two or more effective causes of delays and those causes shall be equal in causative potency. The difficulty in such a scenario is to determine the liability of the damages caused by the delays.
Justice Irfan Saadat Khan of the Supreme Court has recently penned down a brilliant judgment on this concept. Brief factual background of the case is that contractor filed suit before civil court for damages on the basis of delays allegedly caused by the employer, which was decreed in his favor. The same was challenged before the Lahore High Court, but of no avail. Hence, Petition for Leave to Appeal was filed before the Supreme Court. The courts below attributed the delays to the employer rather then the contractor. On this basis, they favored the contractor.
The employer took the Court through documentary evidence and records, and showed that how the delays in the completion of the project work cannot solely be attributed to the employer alone and how the contractor was equally responsibly for the same. The employer established this point before the Court. However, the contractor also alleged certain delays on the part of the employer, which were admitted and true. The Court reached the conclusion that the delays were caused by both of the parties equally and they both shall bear their own cost/damages.
However, the Court delved into the concept of concurrent delays which is new to our jurisdiction. The Court benefited from UK jurisdiction law and judgments and expounded different scenarios of concurrent delays and its examples. For instance, if the delays are caused by two events, one is relevant and the other is not. The contractor cannot be burdened for the event not relevant. Bad weather later accompanied by shortage of labor will be considered as relevant factor and shortage of labor as not relevant event. The contractor cannot be said to be responsible for the delay due to the shortage of labor as the bad weather would cause delay even if there was no shortage of labor. The event which is inevitably consequential for the delay in any event, will be considered relevant event. If that event is followed by another event owing to the contractor or either party, that party cannot be made liable for the event not relevant.
This concept is new to our jurisdiction and it needs to be further developed. We hope this may be furthered in appropriate cases in future.
c.a._296_2015_dt_07-08-2024